Skip to main content
AREConstruction & Evaluation

Schedule of Values Review: Format Requirements, Front-Loading Detection, Line Item Granularity, and Payment Correlation

Covers the architect's responsibility to review and approve the contractor's schedule of values before the first pay application, including how to evaluate format adequacy, detect front-loading, assess line item granularity, and correlate line items to actual payment certification.

2 min read277 words

The Schedule of Values: Your Payment Certification Foundation

Before the contractor submits the first application for payment, there's a document that must exist and must be right: the schedule of values. Get this wrong at the start, and payment certification becomes guesswork for the entire project. Get it right, and you have a defensible, auditable record of what was paid and why.

The schedule of values is a contractor-submitted breakdown of the contract sum into line items that represent distinct portions of work. Each line item carries a dollar value. When the contractor submits a pay application each month on AIA G702/G703, they're claiming a percentage complete for each line item. The architect reviews those claims against site observations and certifies the amount actually earned.

This sounds straightforward. In practice, there are two major problems that arise from a poorly reviewed schedule of values. First is front-loading: the contractor intentionally assigns inflated values to early work items, collecting more money in early payment periods than the actual cost of that work justifies. This shifts financial risk to the owner and creates a situation where the contractor is ahead of the actual work on every payment. Second is insufficient granularity: when line items are too broad, the architect cannot correlate claimed percentages to observable work in the field. You can't certify that 40% of a $500,000 line item called 'Building Construction' is complete. That's not a usable line item.

The ARE tests your ability to evaluate the schedule of values as an architect, not as a contractor's accountant. You need to know what makes a good schedule, what red flags indicate front-loading, and how the schedule connects to every subsequent payment certification for the entire project.

Want to track your progress and access more study tools?

Create a free account