Skip to main content
AREConstruction & Evaluation

Payment Disputes and Withholding: Defective Work, Incomplete Work, Subcontractor Claims, and Owner's Right to Withhold

How the architect evaluates grounds for withholding or nullifying payment certificates under A201, including defective work, subcontractor payment failures, third-party claims, and the contractor's remedies when payment is improperly withheld.

2 min read240 words

When the Architect Puts the Brakes on Payment

The architect's payment certification is not a rubber stamp. Under AIA A201-2017 Section 9.5.1, the architect has explicit authority to withhold a Certificate for Payment or to nullify a certificate already issued, but only to protect the owner from loss. This is one of the architect's most significant construction administration powers and one of the most litigated.

Seven specific grounds justify withholding: un-remedied defective work, third-party claims without adequate security, failure to pay subcontractors or suppliers, evidence the work cannot be completed for the unpaid balance, damage to the owner or separate contractors, evidence the project will not finish on time with insufficient funds to cover delay damages, and repeated failure to carry out the work per contract documents.

The distinction between withholding and nullifying matters. Withholding means the architect declines to issue a new certificate. Nullifying means the architect revokes a certificate already issued. Both require the same threshold: protecting the owner from loss for which the contractor is responsible. When the grounds for withholding or nullifying are removed, the architect must issue a new certificate for the amounts previously withheld.

The contractor is not without recourse. If the architect fails to issue a certificate within 7 days of receiving the application, or if the owner fails to pay within 7 days of the contractor's written notice, the contractor may stop work. The contract time and sum are then adjusted for costs the contractor reasonably incurred during the stoppage.

Want to track your progress and access more study tools?

Create a free account