Schedule of Values and Progress Assessment: Percentage Complete, Stored Materials, Retainage, and Payment Correlation
Covers the schedule of values as a tool for tracking construction progress and correlating it to payment applications. Addresses percentage complete assessment, stored materials accounting, retainage mechanics, and the architect's role in certifying payments based on observed work in place versus the contractor's claimed progress.
The Schedule of Values as a Progress Tracking Tool
The schedule of values (SOV) is the contractor's line-item cost breakdown of the work, submitted before the first payment application. It subdivides the total contract sum into individual work items (sitework, foundations, structural steel, mechanical systems, etc.) with dollar amounts assigned to each. The SOV serves as the baseline against which the architect evaluates construction progress and payment requests.
When the contractor submits a monthly application for payment using AIA G702 (Application and Certificate for Payment) and G703 (Continuation Sheet), each line item on the SOV shows the total value, work completed to date (both from prior periods and this period), stored materials not yet installed, total completed and stored, percentage complete, retainage, and the net amount due. The architect reviews this data against observed work in place during site visits.
Percentage complete on each line item should correlate with what the architect actually sees on site. If the SOV shows structural steel 60% complete but the architect's observation shows only the lower three floors of a seven-story building erected, the claimed percentage needs scrutiny. This correlation between the SOV and actual work is a primary function of construction observation under Objective 2.3.
Retainage is the percentage of each payment withheld by the owner as security against incomplete or defective work. Standard practice sets retainage at 5-10% of each payment, with the amount held until substantial completion. Stored materials represent items purchased and delivered but not yet incorporated into the work. The architect must verify that stored materials are properly protected and insured before certifying their value in a payment application.
Want to track your progress and access more study tools?
Create a free account