Construction Change Directives (CCDs): Disputed Changes, Interim Direction, Cost Determination Methods, and A201 Procedures
Covers construction change directives as the mechanism for directing disputed changes during construction. Addresses CCD issuance authority (owner and architect), the contractor's obligation to proceed, cost determination methods under A201 Section 7.3, interim pricing, and the path from CCD to change order resolution.
CCDs: Directing Work When the Parties Disagree
A construction change directive (CCD) is a written order prepared by the architect and signed by the owner and architect, directing a change in the work before the owner and contractor agree on the adjustment to the contract sum or contract time. Under A201-2017 Section 7.3, a CCD is used when the owner and architect want work to proceed but the contractor disputes the cost, time, or both.
The CCD fills a critical gap between change orders and minor changes. A change order requires all three parties to agree. A minor change (ASI) cannot affect cost or time. But what happens when a change clearly affects cost or time and the parties cannot agree on the numbers? The CCD allows the owner to direct the contractor to proceed with the work while the cost and time disputes are resolved.
The contractor is obligated to promptly perform the work described in a CCD. This obligation exists even if the contractor disagrees with the cost or time specified. The contractor's remedy is to pursue the cost and time dispute through the contract's claims procedures, not to refuse to perform the work.
CCDs require only two signatures: the owner and the architect. The contractor's signature is not required precisely because CCDs address situations where the contractor disagrees. Once the cost and time are eventually agreed upon, the CCD is converted to a change order with all three signatures. Until then, the CCD authorizes the work and the cost is determined through the methods specified in A201 Section 7.3.4.
A CCD can direct changes in scope, method, or sequence of work. It can increase or decrease the contract sum. The key feature is that it provides interim authorization to proceed while preserving each party's right to dispute the financial terms.
Want to track your progress and access more study tools?
Create a free account