Skip to main content
AREProject Management

G-Series Change and Administration Forms: Change Orders (G701), CCDs (G714), ASIs (G710), and RFIs (G716)

AIA G-Series forms that govern changes and administration during construction, including change orders, construction change directives, architect's supplemental instructions, and requests for information.

2 min read228 words

G-Series Forms: The Architect's Change Management Toolkit

Construction never goes exactly according to plan. Site conditions shift, owners refine their vision, contractors spot conflicts in the documents. Every one of those moments requires a formal mechanism for communicating and authorizing changes. That is where the AIA G-Series forms come in.

Four forms sit at the center of construction-phase change management. G701 (Change Order) formalizes changes that all three parties, owner, contractor, and architect, have agreed upon. G714 (Construction Change Directive) lets the owner and architect direct changes even when the contractor hasn't yet agreed on price or time adjustments. G710 (Architect's Supplemental Instructions) handles minor clarifications and interpretations that don't touch the contract sum or contract time. And G716 (Request for Information) gives any party a standardized way to ask questions about the contract documents without authorizing additional cost or time.

For the PjM exam, you need to know when each form applies, who signs it, and what authority it carries. Mixing them up is one of the most common traps on the test. A change directive is not a change order. An ASI is not an RFI. Each form has a specific scope and specific limits, and getting those boundaries wrong on the exam means getting the question wrong.

This topic covers the purpose, parties, and contractual limits of each form so you can confidently match any construction scenario to the correct G-Series document.

Want to track your progress and access more study tools?

Create a free account