Change Orders: Initiation, Pricing, Negotiation, Owner Approval, and Documentation Under G701
Covers the change order process from initiation through execution, including the roles of the architect, owner, and contractor. Addresses pricing methods, negotiation procedures, owner approval requirements, documentation using AIA G701, and the relationship between change orders and other change instruments under A201-2017.
Change Orders as the Primary Contract Modification Instrument
A change order is a written instrument prepared by the architect and signed by the owner, contractor, and architect, documenting their agreement on a change in the work, the adjustment to the contract sum, and the adjustment to the contract time. Under AIA A201-2017 Section 7.2, a change order is the only contract modification that requires all three parties to agree.
Change orders are the primary formal mechanism for modifying the construction contract after execution. They address changes that affect the contract sum, contract time, or both. Common triggers include owner-requested scope additions or deletions, design errors or omissions discovered during construction, unforeseen site conditions requiring design modifications, code requirement changes, and value engineering proposals.
The standard AIA form for change orders is G701-2017. This form documents the change description, the adjustment to the contract sum (increase or decrease), the adjustment to the contract time (extension or compression), and the signatures of all three parties. Once executed, the change order becomes part of the contract documents.
The architect's role in the change order process is to prepare the change order document, not to authorize the expenditure. The owner authorizes the financial commitment by signing the change order. The contractor agrees to the scope, cost, and time by signing. The architect's signature confirms that the change is documented and will be used to determine conformance of the work going forward.
Change orders are distinguished from construction change directives (CCDs), which do not require the contractor's agreement, and from minor changes (ASIs), which do not affect cost or time. When all three parties agree on the change, a change order is the appropriate instrument.
Want to track your progress and access more study tools?
Create a free account