Post-Bid Negotiation and Scope Adjustment: Deductive Alternates, Re-Bidding Criteria, Schedule Acceleration, and Phasing Options

How architects advise owners on post-bid cost adjustment strategies including exercising deductive alternates, evaluating re-bidding criteria, assessing schedule acceleration options, and structuring phasing to bring projects within budget after bids are received.

2 min read234 words

Post-Bid Negotiation: What Happens When the Numbers Don't Work

Bids are received. The owner looks at the numbers. They're over budget. Now what?

Post-bid negotiation is the structured process that follows when bids exceed the owner's budget or when the project scope needs adjustment before a contract can be executed. It's a distinct phase with distinct tools. The architect's role is to advise the owner on which tool fits which situation and to ensure that whatever is decided gets properly documented before a contract is signed.

The key tools are: exercising deductive alternates (scope reductions that were bid as separate line items), negotiating directly with the apparent low bidder to reduce scope or price, evaluating whether re-bidding is appropriate, and assessing whether schedule acceleration or phasing can change the cost picture.

Each tool carries different contractual implications and different risks. Deductive alternates are the cleanest because they were priced as part of the bid; accepting them doesn't require additional negotiation. Post-bid negotiation with a single bidder works but requires careful documentation and must stay within the bounds of competitive bidding rules on public projects. Re-bidding is expensive and time-consuming but sometimes necessary. Schedule acceleration may seem like it solves a timeline problem but often adds cost rather than reducing it.

The ARE tests this area within Objective 1.3, which asks candidates to analyze aspects of the contract or design to adjust project costs during bidding. Post-bid negotiation is a significant piece of that.